  • ELECTRICITY SUPPLY TO CHERKASY AND THE REGION RESTORED

    Today at 11:57, 110 kV open switchgear at SS 330 kV Poliana of Tsentralna Power System of SE NPC Ukrenergo was completely de-energised when switching on the 2 system of 110 kV bus bars after the scheduled repair of 110 kV equipment due to the action of bars differential protection (because of the damaged bar disconnector ShR-110 kV of connection “BKhO-2” from 1 system of 110 kV bus bars).

    As a result, 7 110 kV substations of PJSC “Cherkasyoblenergo” (Khutory, Sosnivka, Zakhidna, Lesky, BKhO, Sokyrne, Dakhnivka) with the load of 10.3 MW (treatment facilities and water utility of Cherkasy, a number of industrial, agricultural consumers and households in the region) were de-energised.

    Because of the coherent work of the employees of SS Poliana, Cherkasy repair and operation centre of NPC Ukrenergo and dispatchers, treatment facilities and water utility of Cherkasy were supplied with power at 12:59, while at 13:09, power supply to all consumers in the region was fully restored.

    Share:

    You may be interested