    We are actively developing our cooperation with the EIB (European Investment Bank). It invests in large-scale infrastructure projects in Ukraine. Thanks to cooperation the usage of installed capacity of nuclear power plants is significantly increased, emissions of harmful substances are reduced, as well as the stability of electricity supply to consumers is increased.

    Joint projects:

    The key purpose of the project is to ensure the maximum use of the installed capacity of the Rivnenska and Khmelnytska NPPs, replacing the electricity generated by thermal power plants with the cheaper electricity generated by nuclear power plants, which in turn will save gas, fuel oil and coal and reduce emissions of harmful substances and greenhouse gases, improve the stability of electricity supply to consumers of the Kyiv power node due to the transit of surplus power from the western part of the IPS of Ukraine where both NPPs are located.

    Legal agreements:

    • Financial Agreement between Ukraine and the EIB signed on 20.10.2008, ratified on 01.04.2009 (Law of Ukraine No. 1215-VI), effective since 15.09.2009.
    • Project Agreement between Ukrenergo and the EIB signed on 20.10.2008, effective since 15.09.2009.
    • Sub-loan Agreement between the Ministry of Finance, the Ministry of Energy and Coal Industry, the NEURC, and Ukrenergo No. 28020-02/128 dated 08.10.2008 (with changes and amendments dated 07.09.2012, 01.07.2019).

    Loan total amount – EUR 300.0 million, of which:

    EIB loan – EUR 150 million. The maturity date is 31.12.2020 (being extended to 31.12.2023).

    EBRD loan – EUR 150 million. The maturity date is 31.10.2018.

    Project Description:

    • Construction of the OHL 750 kV Rivnenska NPP–Kyivska – matched funding by the EBRD and the EIB;
    • Construction of a diversion of the OHL 750 kV Khmelnytska NPP–Chornobyl NPP to the SS 750 kV Kyivska – matched funding by the EBRD and the EIB;
    • Expansion and modernization of the SS 750 kV Kyivska by installing a second 750/330 kV autotransformer – matched funding by the EBRD and the EIB;
    • Construction of a diversion of the OHL 330 kV Chornobyl NPP–Pivnichna to SS 750 kV Kyivska – the EIB funding;
    • Rehabilitation of the SS 330 kV Brovarska – the EIB funding (additional component due to saved EIB loan funds);
    • Consulting Services: procurement and project management assistance, technical support of the Project Management Unit – the EBRD and EIB funding.

    The construction of the OHL 750 kV Rivnenska NPP–Kyivska and a diversion of OHL 750 kV Khmelnytska NPP–Chornobyl NPP to Kyivska substation was completed and a second autotransformer was installed at the 750 KV Kyivska substation (the facilities are commissioned), and the construction was completed at the diversion of OHL 330 kV Chornobyl NPP–Pivnichna to the SS 750 kV Kyivska (commissioning is planned for the 1st quarter of 2021).

    The rehabilitation contract of the SS 330 kV Brovarska is being implemented.

    The key purpose of the project is to improve the reliability of the operating modes of the southern part of the IPS of Ukraine by removing network constraints on the power output of Zaporizka NPP, stabilizing the voltage in the Pivdenna Power System, increasing the transfer capacity of profiles in the southern part of the IPS of Ukraine by strengthening the connection of the Kakhovsky power node with the trunk grids of the IPS of Ukraine.

    Legal agreements:

    • Financial Agreement between Ukraine and the EIB signed on 16.09.2011, ratified on 18.09.2012 (Law of Ukraine No. 5256-VI), effective since 03.12.2012.
    • Project Agreement between Ukrenergo and the EIB signed on 16.09.2011, effective since 03.12.2012.
    • Sub-loan Agreement between the Ministry of Finance, the Ministry of Energy and Coal Industry, the NEURC, and Ukrenergo No. 15010-03/75 dated 02.07.2012 (with changes and amendments dated 01.07.2019).

    Loan total amount – EUR 335.0 million, of which:

    EIB loan – EUR 175 million. The maturity date is 31.12.2020 (being extended to 31.12.2023).

    EBRD loan – EUR 160 million. The maturity date is 31.12.2021.

    Project Description:

    • Construction of the OHL 750 kV Zaporizka NPP–Kakhovska, including a repair and maintenance station and a fibre-optic communication line (FOCL) – matched funding by the EBRD and the EIB;
    • Construction of the 750 KV Kakhovska substation with the installation of the first and second autotransformers with a capacity of 1,000 MVA each, including an automated process control system – matched funding by the EBRD and the EIB;
    • Construction of a diversion of the OHL 330 kV Novokakhovska–Ostrovska to the SS 750 kV Kakhovska, including rehabilitation of the 330 kV Ostrovska substation, installation of fibre-optic lines along the OHL 330 kV Novokakhovska–Kakhovska – matched funding by the EBRD and the EIB;
    • Construction of a diversion of the OHL 330 kV Novokakhovska–Khersonska to the SS 750 KV Kakhovska, including rehabilitation of the SS 330 kV Khersonska, installation of fibre-optic lines along the OHL 330 KV Kakhovska–Khersonska – matched funding by the EBRD and the EIB;
    • Construction of the SS 330 kV Zakhidna with diversions of OHL 330 kV – the EBRD funding (additional component due to saved funds of the EBRD loan);
    • Installation of fibre-optic communication lines (FOCL), namely reconstruction of the 330 kV overhead line with the replacement of lightning protection cable with optical ground wire (OPGW) with the installation of FOCL station equipment in the southern Ukraine (Kyiv, Vinnytsia, Kirovohrad, Cherkasy, Poltava, Dnipropetrovsk, Zaporizhzhia, Kherson, Mykolaiv, and Odesa regions) – the EIB funding (additional component due to saved funds of the EIB loan).

    The construction of the 750 kV overhead line Zaporizka NPP–Kakhovska is completed (the overhead line was put under load on the side of Zaporizka NPP on 24.11.2020, commissioning is planned for the third quarter of 2021), which will enable removing network constraints on the output of the full capacity of Zaporizka nuclear power plant and increase the output from 5,300 to 6,000 MW.

    As part of the project, the construction is completed at the SS 750 kV Kakhovska substation, a diversion of the OHL 330 kV Novokakhovska–Ostrovska and a diversion of the OHL 330 kV Novokakhovska–Khersonska to the 750 kV Kakhovska substation (the facilities are commissioned).

    The construction contract of the 330 kV Zakhidna substation is in progress.

    As part of an additional component for the FOCL installation, international competitive bidding is being finalised for sub-package 1 dedicated to the reconstruction of 330 kV overhead lines with the replacement of the lightning protection cable with the optical ground wire (OPGW) in the Dniprovska, Pivdenna, and Pivdenno-Zakhidna Power Systems. As part of sub-package 2 “Installation of FOCL station equipment” and sub-package 3 “Construction of cable communication lines” the tender documentation for international competitive bidding is being developed.

    The key purpose of the project is to improve the efficiency and reliability of the IPS of Ukraine for its integration with the European Network of Transmission System Operators for Electricity (ENTSO-E). The project is part of NPC Ukrenergo’s comprehensive program for substations automation funded with loans provided by the EBRD, EIB, IBRD, and KfW.

    Legal agreements:

    • Guarantee Agreement between Ukraine and the EIB signed on 24.05.2018 (ratified by the Law of Ukraine No. 1035-IX of 02.12.2020).
    • Financial Agreement between Ukraine and the EIB signed on 24.05.2018.
    • Repayment Agreement between the Ministry of Finance, the NEURC and Ukrenergo No. 13010-05/128 dated 24.06.2020.

    The EIB loan amount is EUR 136 million.

    Project Description:

    The project provides for the rehabilitation of 9 substations of the Dniprovska PS with the implementation of automated process control systems (APCS), including:

    • Seven 330 kV substations in Dnipropetrovsk region (Nikopolska, Prometei, Pivdenna, Pershotravneva, Kamianska, Pavlohradska, and Hirnycha),
    • One 330 kV substation in Zaporizhzhia region (Melitopilska),
    • One 750 kV substation in Donetsk region (Pivdennodonbaska).

    NPC Ukrenergo has developed feasibility studies for all substations and received positive expert reports on the feasibility studies.

    The international consultant Mott MacDonald (UK) engaged by the EIB prepared a Fact Finding Study and developed the pre-qualification documentation that was approved by the EIB.

    Currently, the preliminary qualification is in progress, and the Consultant is developing the tender documentation for international competitive bidding.