default-logo

Ukrenergo and Moldelectrica: cooperation towards integration into ENTSO-E continues

16 July 2018
On July 11-12, Chisinau hosted a working meeting of the representatives of SE NPC Ukrenergo and SE Moldelectrica aimed at discussing a wide range of issues regarding synchronization with ENTSO-E.

TRAINING AS A PLEDGE OF SAFETY

12 July 2018
A joint firefighting training for regular personnel and representatives of the State Emergency Service of Ukraine took place at 330 kV SS “Koziatyn” of Pivdenno-Zakhidna PS.

Launch of 330 kV “Kryvorizka” Substation Reconstruction

09 July 2018
330 SS kV “Kryvorizka” became the first Ukrenergo substation where works on the reconstruction of basic equipment started with the financial support provided by the Government of the Federal Republic of Germany.

POWER SYSTEM SHOULD BE CHANGED TO REACH AN INCREASED RES GENERATION SHARE – V. KOVALCHUK

06 July 2018
On July 4, Vsevolod Kovalchuk participated in the conference “Renewable Energy – Energy for Peace and Democracy” held within the framework of the German-Ukrainian Forum in Lviv.

UKRENERGO WILL PARTICIPATE IN XVI INTERNATIONAL ENERGY FORUM

04 July 2018
Ukrenergo will participate in the International Forum “Fuel and Energy Complex of Ukraine: today and tomorrow” to be held this year on 6-8 November in Kyiv at the International Exhibition Centre (15 Brovarskyi Prospekt).

A new autotransformer has been commissioned at 750 kV SS “Vinnytska”

04 July 2018
A new autotransformer AT-4 with the capacity of 125 MWA has been commissioned at 750 kV SS “Vinnytska” of Pivdenno-Zakhidna PS.

UKRENERGO CONDUCTED A LARGE-SCALE TRAINING FOR DISPATCHERS OF THE INTEGRATED POWER SYSTEM

26 June 2018
On June 26, SE NPC Ukrenergo conducted a sectoral emergency training in the integrated power system (IPS) of Ukraine

Ukrenergo became a partner of the first Ukrainian fantasy film “The Bobot”

23 June 2018
In the framework of its corporate social responsibility program, SE NPC Ukrenergo became a partner of a new Ukrainian sci-fi film for children “The Bobot” (the Ukrainian release is called “Bobot and Power of the Universe”)

Substation 750 kV Zakhidnoukrainska commissioned new reactors

22 June 2018
Substation (SS) 750 kV Zakhidnoukrainska commissioned and connected to the export overhead line 750 kV Zakhidnoukrainska – Albertirsha three lines of reactors R-14. The equipment is replaced in the framework of Ukrenergo Investment Program for 2018

Ukraine and Moldova continue cooperation towards integration into ENTSO-E

22 June 2018
The Ministry of Energy and Coal Industry held a joint Ukrainian-Moldovan meeting headed by Deputy Minister on European Integration Nataliia Boiko and the Minister of Economy and Infrastructure of the Republic of Moldova Chiril Gaburici